Tender overview
Choose the delivery mix for a sample AED 6m fit-out.
Plan at a glance
Delivery combinations
Compare eight ways to deliver the three packages.
0 = own crew · 1 = supplierPackage order: enabling works, MEP, partitionsCompare all scenarios ›
Compare scenarios
Review how each award affects contribution, handover and peak funding for this sample tender.
Delivery alternatives
Tender report
Review the preferred award, package contribution and weekly crew demand.
No feasible award
The current limits rule out all delivery mixes. Review the excluded options or adjust the assumptions.
Package contribution
AEDSales less direct cost, before site overhead.
Weekly crew demand
Crew unitsModel checks
Review the checks behind the current recommendation.
Validation & run results
Source figures and calculation rules
| Package | Allocated sales, AED k | In-house cost / weeks / units | Subcontract cost / weeks / units |
|---|---|---|---|
| Enabling | 1,300 | 920 / 3 / 2 | 1,040 / 2 / 1 |
| MEP first fix | 2,700 | 1,880 / 6 / 4 | 2,010 / 4 / 1 |
| Partitions | 2,000 | 1,350 / 5 / 3 | 1,490 / 4 / 1 |
The enabling package starts in week one. MEP and partitions may overlap in distinct released areas after enabling completes. All three packages must be delivered. Site overhead is AED 75,000 per project week. External quotes include the same scope; the quote slider changes only the external MEP price. Shared headroom is already available at the modeled rates.
Direct costs are paid uniformly across active weeks, before end-of-week receipts. Each package earns 95% of its allocated sales at completion plus the selected collection lag. The remaining 5% is received four weeks after the final package payment. Opening cash is zero. Peak funding is the largest interim shortfall. No tax, financing, corporate overhead or claims are modeled. Replace every payment assumption with contract terms for a real tender.
All eight delivery mixes and every precedence-compliant whole-week start within the deadline are evaluated. The model maximizes contribution, breaks ties on lowest peak funding and then earliest finish. No AI estimates or forecasts are used in this example.
Pilot services
Replay a past tender with your estimating and commercial teams. View the advisory pilot.
Free-zone renewal operations
Compare staff transfers and overtime against service deadlines.
Open renewal shift plannerBring one historical bid.
Bring a redacted priced bill of quantities, comparable subcontract quotes, weekly crew availability and the payment schedule.
Reconcile the estimate
Confirm quantities, exclusions and the cost of each delivery option.
Test the trade-offs
Change a quote, crew limit or collection date and compare feasible plans.
Review the decision
Take the recommended mix, threshold prices and funding needs to the bid committee.